How might Activity resource estimating affect estimated activity duration?
Category:
personal finance
financial planning
The number of resources assigned to an activity also affects its estimated duration. The effort estimate related to how many hours will be spent performing an activity. The activity duration estimate includes the effort as well as how much time passes on a calendar in order to generate the project schedule.
Besides, why are activity resources generally estimated before activity durations?
Estimate Activity Durations is the process of estimating the number of work periods needed to complete individual activities with estimated resources. The key benefit of this process is that it provides the amount of time each activity will take to complete, which is a major input into the Develop Schedule process.
Beside above, what are the examples of inputs to the estimate activity durations process?
Inputs such as the schedule management plan, activity list, activity attributes, resource calendars, project scope statement, risk register, resource breakdown structure are necessary to come up with a reasonable estimate for each task involved in the project lifecycle.